This checklist identifies Key Commissioning Test Requirements and Key Preparations and Cautions for a building's return, relief, and exhaust systems. When writing a test, use this checklist to help ensure that these key areas have been covered. The buttons following the checklist items link to supporting information within the Functional Testing Guide and the Control System Design Guide.

Link Legend:

Test Guidance Test
Guidance
Tips Tips Typical Problems Typical
Problems
Design Issues Design
Issues
Control System Design Guide Control System
Design Guide

Key Commissioning Test Requirements

The following key commissioning test requirements for return, relief, and exhaust systems are similar to the requirements associated with the supply fans and drives. Note that many of the following test requirements pertain to issues that should be addressed and checked during design, construction, or initial start-up and TAB in order to successfully test each system.Tips

The following key commissioning test requirement for return, relief, and exhaust systems are similar to the requirements associated with the supply-side distribution system.Tips

Key Preparations and Cautions